Construction Update July 2019

Existing and future residents will have noticed plenty of changes taking place at Ashbury over recent months. Civil construction of Stages 8, 9, 10 and 11 is now complete, with new residents having taken possession of their land in early July. All roads in these stages have now been asphalted and footpaths have been concreted and soil testing can now commence, all of which means that future residents in these stages will begin building their new homes very soon. Ashbury’s newest round of residents will be joining the existing community in no time!

Construction Update March 2019

Construction updates at Ashbury.

Construction is progressing well on Stages 8 to 11 with titles expected by June 2019. Click on the video below and watch Ashbury come to life.

Wetlands Update February 2019

You may have noticed a fluctuation in water levels in the wetlands area alongside Horseshoe Bend Rd.  These are due to construction works currently being undertaken at Ashbury and will continue from now to the end of May 2019.  The works relate to the construction of a temporary drainage facility, south of the wetlands reserve, and an upgrade to the drainage pipes running under Horseshoe Bend Rd. The temporary drainage facility is to provide additional drainage capacity until the Council Sparrowvale wetland system is complete.

Construction Update January 2019

It’s all good news on the civil construction front for purchasers of lots in Stages 8 – 11. Construction of key infrastructure works are now well underway; water and sewer works have been completed, and preliminary works on roads have commenced, along with curb and channel works underway in Stages 10 and 11  and early in the New Year for Stages 8 and 9.

With all works on track to be completed by May 2019, purchasers can look forward to receiving titles and settling on their lots in June.

Other Works

Adding to Ashbury’s appeal to young families, a new playground in Stage 9 is also expected to be completed in April next year. Surrounded by River Red Gums, the playground will feature an assortment of play equipment, suitable for children of ages, as well as a shaded picnic area – making it the perfect place to relax and make the most of outdoor living at Ashbury. 

Construction Update August 2018

With great winter weather, our construction team have been busy. Purchasers in Stages 4 to 7 have received their titles and we’re expecting our first residents to call Ashbury home in the coming months. Civil works have now commenced on Stages 8 to 11 with titles expected in the second quarter of 2019. Click on the video below and enjoy a birds eye view of Ashbury.

Construction Update April 2018

Due to the good weather experienced over summer, construction at Ashbury has progressed very well.

All civil engineering services have been installed for stages 4 -7, concrete works are well under way and final roadworks are about to commence.

Construction on all four Stages is on target for completion in June 2018.

Installation of street landscaping to the estate’s entryways, including turf, street trees and the striking entry sculpture is nearing completion.

Construction Update March 2017

Welcome to the first video update of the construction and infrastructure works at Ashbury.

With the recent period of fine weather, construction activity has progressed quickly and we are delighted to see the first few stages of land within the Ashbury community now taking shape.

Key infrastructure works in progress at Ashbury

Victoria, Australia – Works on the delivery of several key areas of infrastructure at Ashbury estate in Armstrong Creek are under way, including major upgrades to Boundary Road at the intersection of Ashbury Boulevard. Also being carried out is the installation of street lighting in Stages 1-3 of the estate, the laying down of new water mains and an upgrade of the existing fibre optic network. This critical work will ensure the completion of the first stages of Ashbury on program.

Construction Update

'Construction on Stages 1, 2 and 3 is nearing completion with only compliance testing of services and final pavement layer works outstanding. All services have been installed, including electrical and communications cables, street lights, water and sewer reticulation, and drainage connections. Street signs are currently being installed and asphalting of the roads will commence within the next couple of days.